ITAC Assessment: AM0675
ITAC logo
ITAC Assessment: AM0675
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2015
Principal Product angiography catheters
NAICS 339112: Surgical and Medical Instrument Manufacturing
SIC 3841: Surgical and Medical Instruments and Apparatus
Sales Range $10
M
to 50
M
# of Employees 220
Plant Area 85,000
ft2
Annual Production 600,000
pieces
Production Hrs. Annual 8,424
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $198,133 3,189,357
kWh
Electricity Demand $63,556 9,659
kW-mo/yr
Electricity Fees $20,763 -
Natural Gas $39,208 3,689
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $71,780 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,210

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings
01 2.4322: Use or replace with energy efficient substitutes $31,650 $2,210 $25,900
454,000
kWh
$5,750
-
kW-mo/yr
- - - -
02 2.7226: Use computer programs to optimize hvac performance $8,020 $60 - - - $8,020
-
MMBtu
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $6,670 $610 $5,960
104,570
kWh
$710
-
kW-mo/yr
- - - -
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $5,990 - - - - - $5,990
-
lb
-
05 2.3131: Reschedule plant operations or reduce load to avoid peaks $4,250 - - $4,250
-
kW-mo/yr
- - - -
06 2.8121: Apply for tax-free status for energy purchases $14,950 $2,000 - - $2,990 - - $11,960
07 2.2511: Insulate bare equipment $250 $130 $250
4,400
kWh
- - - - -
TOTAL RECOMMENDED $71,780 $5,010 $32,110
562,970
kWh
$10,710
-
kW-mo/yr
$2,990 $8,020
-
MMBtu
$5,990
-
lb
$11,960
TOTAL IMPLEMENTED $33,210 $2,060 - $4,250
-
kW-mo/yr
$2,990 $8,020
-
MMBtu
$5,990
-
lb
$11,960
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings Solid Waste (non-haz) Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs