ITAC Assessment: AM0657
ITAC logo
ITAC Assessment: AM0657
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Poultry Products
NAICS 311615: Poultry Processing
SIC 2015: Poultry Slaughtering and Processing
Sales Range $100
M
to 500
M
# of Employees 1,300
Plant Area 216,000
ft2
Annual Production 407,000,000
lb
Production Hrs. Annual 8,568
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,495,192 36,568,800
kWh
Electricity Demand $878,618 71,275
kW-mo/yr
Electricity Fees $543 -
Natural Gas $189,985 52,030
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $42,245 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,055

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $18,150 $16,680 $12,770
311,570
kWh
$5,380
-
kW-mo/yr
02 2.7142: Utilize higher efficiency lamps and/or ballasts $14,770 $21,200 $10,400
254,000
kWh
$4,370
-
kW-mo/yr
03 2.7135: Install occupancy sensors $4,420 $450 $2,340
57,000
kWh
$2,080
-
kW-mo/yr
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $2,540 - $1,800
44,000
kWh
$740
-
kW-mo/yr
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,365 $330 $1,670
40,880
kWh
$695
-
kW-mo/yr
TOTAL RECOMMENDED $42,245 $38,660 $28,980
707,450
kWh
$13,265
-
kW-mo/yr
TOTAL IMPLEMENTED $23,055 $17,010 $16,240
396,450
kWh
$6,815
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs