Assessment Year | 2014 |
---|---|
Principal Product | Ice Cream |
NAICS | 311520: Ice Cream and Frozen Dessert Manufacturing |
SIC | 2024: Ice Cream and Frozen Desserts |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
62,000
ft2
|
Annual Production | 48,000,000
pieces
|
Production Hrs. Annual | 4,250
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $68,482 | 1,892,700 |
kWh
|
$0.036 |
Electricity Demand | $82,995 | 4,961 |
kW-mo/yr
|
$16.73 |
Electricity Fees | $8,208 | - |
|
- |
Natural Gas | $23,590 | 3,935 |
MMBtu
|
$5.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $16,193 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,156 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $6,620 | $9,320 | - |
$6,620
-
kW-mo/yr
|
- | |
02 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,950 | $1,320 | - | - |
$2,950
-
MMBtu
|
|
03 | 2.4324: Replace hydraulic / pneumatic equipment with electric equipment | $2,037 | $4,000 |
$587
15,640
kWh
|
$1,450
-
kW-mo/yr
|
- | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,492 | $3,750 |
$668
17,800
kWh
|
$824
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,476 | $1,000 |
$661
17,630
kWh
|
$815
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $724 | $576 |
$356
9,490
kWh
|
$368
-
kW-mo/yr
|
- | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $677 | $5 |
$303
8,090
kWh
|
$374
-
kW-mo/yr
|
- | |
08 | 2.7135: Install occupancy sensors | $217 | $400 |
$217
5,820
kWh
|
- | - | |
TOTAL RECOMMENDED | $16,193 | $20,371 |
$2,792
74,470
kWh
|
$10,451
-
kW-mo/yr
|
$2,950
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,156 | $16,371 |
$2,205
58,830
kWh
|
$9,001
-
kW-mo/yr
|
$2,950
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs