ITAC Assessment: AM0650
ITAC logo
ITAC Assessment: AM0650
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2014
Principal Product Mechanical springs
NAICS 332613: Spring Manufacturing
SIC 3495: Wire Springs
Sales Range $10
M
to 50
M
# of Employees 118
Plant Area 80,500
ft2
Annual Production 151,630,000
pieces
Production Hrs. Annual 4,250
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $170,356 2,687,750
kWh
Electricity Demand $51,634 6,827
kW-mo/yr
Electricity Fees $4,654 -
Natural Gas $22,206 3,382
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $60,922 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $57,730

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.3131: Reschedule plant operations or reduce load to avoid peaks $17,640 - - $17,640
-
kW-mo/yr
- - - -
02 2.8121: Apply for tax-free status for energy purchases $31,250 $10,000 - - $6,250 - - $25,000
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,060 $1,200 $3,860
60,300
kWh
$1,200
-
kW-mo/yr
- - - -
04 2.3212: Optimize plant power factor $2,335 $6,805 - $2,335
-
kW-mo/yr
- - - -
05 3.6193: Install equipment (eg compactor) to reduce disposal costs $2,190 $4,080 - - - - $2,190 -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $1,050 $605 $210
3,250
kWh
$30
-
kW-mo/yr
- $810 - -
07 2.7135: Install occupancy sensors $540 $550 $540
8,450
kWh
- - - - -
08 2.4314: Use synthetic lubricant $432 - $318
4,969
kWh
$114
-
kW-mo/yr
- - - -
09 2.4231: Reduce the pressure of compressed air to the minimum required $425 $20 $325
5,100
kWh
$100
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $60,922 $23,260 $5,253
82,069
kWh
$21,419
-
kW-mo/yr
$6,250 $810 $2,190 $25,000
TOTAL IMPLEMENTED $57,730 $16,435 $4,610
72,000
kWh
$18,870
-
kW-mo/yr
$6,250 $810 $2,190 $25,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs