Assessment Year | 2012 |
---|---|
Principal Product | Conveyors |
NAICS | 333922: Conveyor and Conveying Equipment Manufacturing |
SIC | 3531: Construction Machinery and Equipment |
Sales Range | $10 M to 50M |
# of Employees | 87 |
Plant Area |
200,000
ft2
|
Annual Production | 1,600
pieces
|
Production Hrs. Annual | 4,723
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $94,172 | 1,782,951 |
kWh
|
$0.053 |
Electricity Demand | $40,206 | 6,336 |
kW-mo/yr
|
$6.35 |
Electricity Fees | $2,244 | - |
|
- |
Natural Gas | $34,046 | 6,476 |
MMBtu
|
$5.26 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $65,600 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $50,385 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $28,900 | $21,800 |
$21,600
407,600
kWh
|
$7,300
-
kW-mo/yr
|
- | - | - | |
02 | 2.7145: Install skylights | $8,500 | $2,560 |
$8,500
161,000
kWh
|
- | - | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,515 | $1,500 |
$5,780
109,000
kWh
|
$1,735
-
kW-mo/yr
|
- | - | - | |
04 | 2.3212: Optimize plant power factor | $6,000 | $13,190 | - |
$6,000
-
kW-mo/yr
|
- | - | - | |
05 | 2.8121: Apply for tax-free status for energy purchases | $13,000 | $1,300 | - | - | - | $2,600 | $10,400 | |
06 | 2.4314: Use synthetic lubricant | $715 | - |
$535
10,090
kWh
|
$180
-
kW-mo/yr
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $485 | $275 |
$75
1,450
kWh
|
$15
-
kW-mo/yr
|
- | $395 | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $485 | $275 |
$75
1,450
kWh
|
$15
-
kW-mo/yr
|
$395 | - | - | |
TOTAL RECOMMENDED | $65,600 | $40,900 |
$36,565
690,590
kWh
|
$15,245
-
kW-mo/yr
|
$395 | $2,995 | $10,400 | ||
TOTAL IMPLEMENTED | $50,385 | $25,150 |
$27,530
519,500
kWh
|
$9,065
-
kW-mo/yr
|
$395 | $2,995 | $10,400 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs