| Assessment Year | 2012 |
|---|---|
| Principal Product | Kitchen and bathroom cabinets |
| NAICS | 337110: Wood Kitchen Cabinet and Countertop Manufacturing |
| SIC | 2434: Wood Kitchen Cabinets |
| Sales Range | $10 M to 50M |
| # of Employees | 150 |
| Plant Area |
200,000
ft2
|
| Annual Production | 60,000
pieces
|
| Production Hrs. Annual | 1,992
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $168,789 | 2,432,130 |
kWh
|
$0.069 |
| Electricity Demand | $94,885 | 12,010 |
kW-mo/yr
|
$7.90 |
| Electricity Fees | $35,915 | - |
|
- |
| Natural Gas | $1,736 | 225 |
MMBtu
|
$7.72 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $181,270 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $180,440 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.3212: Optimize plant power factor | $42,700 | $60,200 | - |
$42,700
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.8121: Apply for tax-free status for energy purchases | $109,000 | $10,900 | - | - | $21,800 | - | $87,200 | |
| 03 | 2.8123: Pay utility bills on time | $9,700 | - | - | - | $9,700 | - | - | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,300 | $17,365 |
$2,560
36,600
kWh
|
$1,740
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,510 | $620 |
$1,480
21,220
kWh
|
$1,030
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.8121: Apply for tax-free status for energy purchases | $12,130 | $1,200 | - | - | $2,430 | - | $9,700 | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $830 | $500 |
$190
2,660
kWh
|
$30
-
kW-mo/yr
|
- | $610 | - | |
| 08 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $100 | - |
$60
890
kWh
|
$40
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $181,270 | $90,785 |
$4,290
61,370
kWh
|
$45,540
-
kW-mo/yr
|
$33,930 | $610 | $96,900 | ||
| TOTAL IMPLEMENTED | $180,440 | $90,285 |
$4,100
58,710
kWh
|
$45,510
-
kW-mo/yr
|
$33,930 | - | $96,900 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs