| Assessment Year | 2011 |
|---|---|
| Principal Product | Glass products |
| NAICS | 327215: Glass Product Manufacturing Made of Purchased Glass |
| SIC | 3231: Glass Products, Made of Purchased Glass |
| Sales Range | $10 M to 50M |
| # of Employees | 175 |
| Plant Area |
201,000
ft2
|
| Annual Production | 3,800
thousand feet
|
| Production Hrs. Annual | 6,072
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $537,346 | 6,404,600 |
kWh
|
$0.084 |
| Electricity Demand | $145,010 | 20,966 |
kW-mo/yr
|
$6.92 |
| Electricity Fees | $15,347 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $105,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $64,170 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $44,300 | $54,200 |
$37,300
439,000
kWh
|
$7,000
-
kW-mo/yr
|
- | - | |
| 02 | 2.3212: Optimize plant power factor | $31,400 | $59,900 | - |
$31,400
-
kW-mo/yr
|
- | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $15,750 | $1,000 |
$12,250
144,000
kWh
|
$3,500
-
kW-mo/yr
|
- | - | |
| 04 | 2.4133: Use most efficient type of electric motors | $5,890 | $28,560 |
$4,440
52,210
kWh
|
$1,450
-
kW-mo/yr
|
- | - | |
| 05 | 2.7124: Make a practice of turning off lights when not needed | $4,120 | - |
$3,470
40,800
kWh
|
$650
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,010 | $910 |
$480
5,600
kWh
|
$60
-
kW-mo/yr
|
- | $1,470 | |
| 07 | 2.8123: Pay utility bills on time | $1,680 | - | - | - | $1,680 | - | |
| TOTAL RECOMMENDED | $105,150 | $144,570 |
$57,940
681,610
kWh
|
$44,060
-
kW-mo/yr
|
$1,680 | $1,470 | ||
| TOTAL IMPLEMENTED | $64,170 | $55,200 |
$53,020
623,800
kWh
|
$11,150
-
kW-mo/yr
|
- | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs