ITAC Assessment: AM0592
ITAC logo
ITAC Assessment: AM0592
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2011
Principal Product Refurbished Blow-Out Preventers
NAICS 333132: Oil and Gas Field Machinery and Equipment Manufacturing
SIC 3533: Oil and Gas Field Machinery and Equipment
Sales Range $10
M
to 50
M
# of Employees 61
Plant Area 57,000
ft2
Annual Production 800
pieces
Production Hrs. Annual 7,440
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,110 2,015,763
kWh
Electricity Demand $47,134 7,958
kW-mo/yr
Electricity Fees $9,872 -
Natural Gas $52,346 5,395
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $104,415 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $59,215

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
01 3.4151: Minimize water usage $36,500 $20,000 - - $(-2,170.0)
-
MMBtu
$38,670
-
Tgal
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $26,200 $11,140 $21,000
357,000
kWh
$5,200
-
kW-mo/yr
- - -
03 3.5314: Use in-process recycling whenever possible $17,240 - - - - - $17,240
04 3.6193: Install equipment (eg compactor) to reduce disposal costs $8,700 - - - - - $8,700
05 2.3212: Optimize plant power factor $6,100 $14,200 - $6,100
-
kW-mo/yr
- - -
06 2.7145: Install skylights $5,600 $100 $5,600
98,200
kWh
- - - -
07 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,770 $500 $3,010
52,000
kWh
$760
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $195 $600 $195
3,140
kWh
- - - -
09 2.7124: Make a practice of turning off lights when not needed $110 - $110
1,900
kWh
- - - -
TOTAL RECOMMENDED $104,415 $46,540 $29,915
512,240
kWh
$12,060
-
kW-mo/yr
$(-2,170.0)
-
MMBtu
$38,670
-
Tgal
$25,940
TOTAL IMPLEMENTED $59,215 $26,540 $29,915
512,240
kWh
$12,060
-
kW-mo/yr
- - $17,240
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs