| Assessment Year | 2011 |
|---|---|
| Principal Product | plastic soft drink bottles |
| NAICS | 326160: Plastics Bottle Manufacturing |
| SIC | 3085: Plastics Bottles |
| Sales Range | $50 M to 100M |
| # of Employees | 68 |
| Plant Area |
425,000
ft2
|
| Annual Production | 1,200,000
lb
|
| Production Hrs. Annual | 6,048
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $839,568 | 14,849,026 |
kWh
|
$0.057 |
| Electricity Demand | $250,248 | 36,588 |
kW-mo/yr
|
$6.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $43,422 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $40,537 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $21,960 | $90 |
$17,250
331,800
kWh
|
$4,710
-
kW-mo/yr
|
- | |
| 02 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,080 | $23 |
$5,560
107,000
kWh
|
$1,520
-
kW-mo/yr
|
- | |
| 03 | 2.8121: Apply for tax-free status for energy purchases | $5,251 | - | - | - | $5,251 | |
| 04 | 2.7132: Install timers on light switches in little used areas | $4,230 | $370 |
$3,600
68,700
kWh
|
$630
-
kW-mo/yr
|
- | |
| 05 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $2,885 | - | - |
$2,885
-
kW-mo/yr
|
- | |
| 06 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $1,575 | - | - |
$1,575
-
kW-mo/yr
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $205 | $225 |
$160
3,050
kWh
|
$45
-
kW-mo/yr
|
- | |
| 08 | 2.8123: Pay utility bills on time | $236 | - | - | - | $236 | |
| TOTAL RECOMMENDED | $43,422 | $708 |
$26,570
510,550
kWh
|
$11,365
-
kW-mo/yr
|
$5,487 | ||
| TOTAL IMPLEMENTED | $40,537 | $708 |
$26,570
510,550
kWh
|
$8,480
-
kW-mo/yr
|
$5,487 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs