ITAC Assessment: AM0586
ITAC logo
ITAC Assessment: AM0586
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Pressure vessel heads
NAICS 332410: Power Boiler and Heat Exchanger Manufacturing
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $10
M
to 50
M
# of Employees 105
Plant Area 192,405
ft2
Annual Production 31,200
pieces
Production Hrs. Annual 5,816
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $209,976 4,165,000
kWh
Electricity Demand $54,689 14,468
kW-mo/yr
Electricity Fees $27,322 -
Natural Gas $752,723 185,070
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $128,735 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $44,515

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $42,330 $42,750 $36,800
695,000
kWh
$5,530
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $30,790 $3,000 $26,765
505,000
kWh
$4,025
-
kW-mo/yr
- -
03 4.426: Modify workload $19,890 - - - - $19,890
04 2.3212: Optimize plant power factor $13,800 $53,380 - $13,800
-
kW-mo/yr
- -
05 2.1113: Reduce combustion air flow to optimum $13,725 - - - $13,725
-
MMBtu
-
06 2.4239: Eliminate or reduce compressed air usage $4,660 $2,040 $4,660
88,000
kWh
- - -
07 2.4314: Use synthetic lubricant $2,195 - $1,910
36,000
kWh
$285
-
kW-mo/yr
- -
08 2.7134: Use photocell controls $1,345 $200 $1,120
21,160
kWh
$225
-
kW-mo/yr
- -
TOTAL RECOMMENDED $128,735 $101,370 $71,255
1,345,160
kWh
$23,865
-
kW-mo/yr
$13,725
-
MMBtu
$19,890
TOTAL IMPLEMENTED $44,515 $3,000 $26,765
505,000
kWh
$4,025
-
kW-mo/yr
$13,725
-
MMBtu
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs