ITAC Assessment: AM0580
ITAC logo
ITAC Assessment: AM0580
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Plate glass
NAICS 327211: Flat Glass Manufacturing
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $100
M
to 500
M
# of Employees 300
Plant Area 750,000
ft2
Annual Production 213,525
ton
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,417,844 58,936,317
kWh
Electricity Demand $479,622 108,666
kW-mo/yr
Electricity Fees $740,029 -
Natural Gas $4,539,982 1,202,318
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $1,570,418 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $141,400

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
01 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat $696,440 $2,700,000 $528,000
12,870,000
kWh
$63,000
-
kW-mo/yr
$(-656,000.0)
-
MMBtu
- - - $761,440
02 4.323: Optimize lot sizes to reduce inventory carrying costs $627,000 - - - - - - $112,000 $515,000
03 4.611: Begin a practice of predictive / preventative maintenance $100,670 - - - - - $1,670 $99,000 -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $83,545 $208,000 $74,720
1,822,530
kWh
$8,825
-
kW-mo/yr
- - - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $21,000 $1,000 $18,800
459,000
kWh
$2,200
-
kW-mo/yr
- - - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $13,930 $150 $12,460
304,000
kWh
$1,470
-
kW-mo/yr
- - - - -
07 3.4111: Use closed cycle process to minimize waste water production $10,780 $1,520 $(-120.0)
(-2,800)
kWh
- - $10,900
-
Tgal
- - -
08 2.4133: Use most efficient type of electric motors $8,950 $34,200 $8,000
195,000
kWh
$950
-
kW-mo/yr
- - - - -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $4,143 $1,880 $460
11,360
kWh
$53
-
kW-mo/yr
- - - - $3,630
10 2.4239: Eliminate or reduce compressed air usage $3,270 $12,630 $2,600
63,500
kWh
$670
-
kW-mo/yr
- - - - -
11 2.4239: Eliminate or reduce compressed air usage $470 $120 $420
10,300
kWh
$50
-
kW-mo/yr
- - - - -
12 2.7145: Install skylights $220 $530 $220
5,410
kWh
- - - - - -
TOTAL RECOMMENDED $1,570,418 $2,960,030 $645,560
15,738,300
kWh
$77,218
-
kW-mo/yr
$(-656,000.0)
-
MMBtu
$10,900
-
Tgal
$1,670 $211,000 $1,280,070
TOTAL IMPLEMENTED $141,400 $36,720 $26,680
651,200
kWh
$3,150
-
kW-mo/yr
- $10,900
-
Tgal
$1,670 $99,000 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs