Assessment Year | 2010 |
---|---|
Principal Product | Rotors for turbines and centrifugal compressors |
NAICS | 335312: Motor and Generator Manufacturing |
SIC | 3621: Motors and Generators |
Sales Range | $100 M to 500M |
# of Employees | 350 |
Plant Area |
300,000
ft2
|
Annual Production | 700
pieces
|
Production Hrs. Annual | 5,680
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,453,570 | 17,130,866 |
kWh
|
$0.085 |
Electricity Demand | $266,048 | 41,316 |
kW-mo/yr
|
$6.44 |
Electricity Fees | $212,186 | - |
|
- |
Natural Gas | $52,549 | 4,141 |
MMBtu
|
$12.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $125,285 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $56,915 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $34,630 | $98,400 | - |
$34,630
-
kW-mo/yr
|
- | |
02 | 2.4239: Eliminate or reduce compressed air usage | $33,740 | $2,160 |
$33,740
362,750
kWh
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $24,200 | $300 |
$20,300
218,000
kWh
|
$3,900
-
kW-mo/yr
|
- | |
04 | 2.4133: Use most efficient type of electric motors | $10,010 | $31,300 |
$8,380
90,120
kWh
|
$1,630
-
kW-mo/yr
|
- | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,400 | $1,500 |
$7,870
84,700
kWh
|
$1,530
-
kW-mo/yr
|
- | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,700 | $1,900 |
$1,140
12,300
kWh
|
$140
-
kW-mo/yr
|
$4,420 | |
07 | 2.7124: Make a practice of turning off lights when not needed | $5,605 | - |
$4,060
43,690
kWh
|
$1,545
-
kW-mo/yr
|
- | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,000 | $1,500 |
$1,670
17,960
kWh
|
$330
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $125,285 | $137,060 |
$77,160
829,520
kWh
|
$43,705
-
kW-mo/yr
|
$4,420 | ||
TOTAL IMPLEMENTED | $56,915 | $36,500 |
$43,420
466,770
kWh
|
$9,075
-
kW-mo/yr
|
$4,420 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs