Assessment Year | 2009 |
---|---|
Principal Product | Wooden baskets |
NAICS | 321920: Wood Container and Pallet Manufacturing |
SIC | 2449: Wood Containers, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
125,000
ft2
|
Annual Production | 2,200,000
pieces
|
Production Hrs. Annual | 2,035
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $83,743 | 947,759 |
kWh
|
$0.088 |
Electricity Demand | $21,847 | 3,876 |
kW-mo/yr
|
$5.64 |
Natural Gas | $59,868 | 8,711 |
MMBtu
|
$6.87 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,145 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $1,870 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,760 | $9,040 |
$2,100
24,100
kWh
|
$660
-
kW-mo/yr
|
|
02 | 2.7145: Install skylights | $2,160 | $2,380 |
$2,160
24,800
kWh
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,870 | $400 |
$1,420
16,300
kWh
|
$450
-
kW-mo/yr
|
|
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $830 | $30 |
$630
7,200
kWh
|
$200
-
kW-mo/yr
|
|
05 | 2.3212: Optimize plant power factor | $690 | $3,010 | - |
$690
-
kW-mo/yr
|
|
06 | 2.4314: Use synthetic lubricant | $425 | - |
$320
3,640
kWh
|
$105
-
kW-mo/yr
|
|
07 | 2.3212: Optimize plant power factor | $410 | $1,630 | - |
$410
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $9,145 | $16,490 |
$6,630
76,040
kWh
|
$2,515
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | $1,870 | $400 |
$1,420
16,300
kWh
|
$450
-
kW-mo/yr
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs