ITAC Assessment: AM0552
ITAC logo
ITAC Assessment: AM0552
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Electrical outlets and switch boxes
NAICS 335314: Relay and Industrial Control Manufacturing
SIC 3613: Switchgear and Switchboard Apparatus
Sales Range $10
M
to 50
M
# of Employees 138
Plant Area 155,000
ft2
Annual Production 160,000,000
pieces
Production Hrs. Annual 5,332
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $298,784 4,382,601
kWh
Electricity Demand $95,369 17,191
kW-mo/yr
Natural Gas $22,522 2,281
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $118,009 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $116,219

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $30,220 $54,170 $25,270
361,000
kWh
$4,950
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $29,920 $1,500 $25,400
362,800
kWh
$4,520
-
kW-mo/yr
- -
03 2.4322: Use or replace with energy efficient substitutes $26,780 $740 $22,400
320,000
kWh
$4,380
-
kW-mo/yr
- -
04 2.8121: Apply for tax-free status for energy purchases $25,920 $240 - - $6,480 $19,440
05 2.7124: Make a practice of turning off lights when not needed $2,790 $500 $2,350
33,580
kWh
$440
-
kW-mo/yr
- -
06 2.2511: Insulate bare equipment $1,790 $400 $1,790
25,620
kWh
- - -
07 2.4314: Use synthetic lubricant $589 - $500
7,148
kWh
$89
-
kW-mo/yr
- -
TOTAL RECOMMENDED $118,009 $57,550 $77,710
1,110,148
kWh
$14,379
-
kW-mo/yr
$6,480 $19,440
TOTAL IMPLEMENTED $116,219 $57,150 $75,920
1,084,528
kWh
$14,379
-
kW-mo/yr
$6,480 $19,440
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs