ITAC Assessment: AM0544
ITAC logo
ITAC Assessment: AM0544
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Envelopes
NAICS 322230: Stationery Product Manufacturing
SIC 2677: Envelopes
Sales Range $10
M
to 50
M
# of Employees 145
Plant Area 114,702
ft2
Annual Production 2,167,000,000
pieces
Production Hrs. Annual 8,496
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $653,326 8,466,418
kWh
Electricity Demand $113,500 16,629
kW-mo/yr
Electricity Fees $12,050 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $90,670 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $90,670

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $27,200 $42,370 $24,050
316,400
kWh
$3,150
-
kW-mo/yr
- - -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $26,350 $2,500 $23,300
306,600
kWh
$3,050
-
kW-mo/yr
- - -
03 2.7124: Make a practice of turning off lights when not needed $16,810 - $14,140
186,100
kWh
$2,670
-
kW-mo/yr
- - -
04 2.7232: Replace existing hvac unit with high efficiency model $10,200 $24,000 $10,200
134,000
kWh
- - - -
05 2.8123: Pay utility bills on time $6,800 - - - $6,800 - -
06 2.4314: Use synthetic lubricant $1,885 - $1,670
21,915
kWh
$215
-
kW-mo/yr
- - -
07 3.7132: Reuse rags until completely soiled $1,040 - - - - - $1,040
08 2.7142: Utilize higher efficiency lamps and/or ballasts $385 - $75
980
kWh
$5
-
kW-mo/yr
- $305 -
TOTAL RECOMMENDED $90,670 $68,870 $73,435
965,995
kWh
$9,090
-
kW-mo/yr
$6,800 $305 $1,040
TOTAL IMPLEMENTED $90,670 $68,870 $73,435
965,995
kWh
$9,090
-
kW-mo/yr
$6,800 $305 $1,040
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs