ITAC Assessment: AM0526
ITAC logo
ITAC Assessment: AM0526
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Foam glass insulation
NAICS 327999: All Other Miscellaneous Nonmetallic Mineral Product Manufacturing
SIC 3299: Nonmetallic Mineral Products, Not Elsewhere Classified
Sales Range $5
M
to 10
M
# of Employees 103
Plant Area 60,000
ft2
Annual Production 20,000
thousand feet
Production Hrs. Annual 8,736
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,053,048 16,839,880
kWh
Electricity Demand $56,505 32,566
kW-mo/yr
Electricity Fees $3,646 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $103,310 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.7141: Lower light fixtures in high ceiling areas $29,900 $18,130 $27,500
295,650
kWh
$2,400
-
kW-mo/yr
- - -
02 2.3212: Optimize plant power factor $15,310 $65,120 - $15,310
-
kW-mo/yr
- - -
03 2.1122: Re-size charging openings or add a movable door on equipment $14,200 $16,400 - - $14,200
-
MMBtu
- -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $10,660 $500 $9,650
103,700
kWh
$1,010
-
kW-mo/yr
- - -
05 3.6192: Use a less expensive method of waste removal $10,500 - - - - $10,500
-
lb
-
06 2.7145: Install skylights $8,650 $8,650 $8,650
93,000
kWh
- - - -
07 2.7124: Make a practice of turning off lights when not needed $5,550 - $5,550
59,700
kWh
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $3,545 $2,300 $2,150
23,000
kWh
$225
-
kW-mo/yr
- - $1,170
09 2.4133: Use most efficient type of electric motors $3,080 $2,850 $2,780
29,900
kWh
$300
-
kW-mo/yr
- - -
10 2.4314: Use synthetic lubricant $1,915 - $1,700
18,300
kWh
$215
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $103,310 $113,950 $57,980
623,250
kWh
$19,460
-
kW-mo/yr
$14,200
-
MMBtu
$10,500
-
lb
$1,170
TOTAL IMPLEMENTED - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs