Assessment Year | 2007 |
---|---|
Principal Product | Footcare and home healthcare products |
NAICS | 339112: Surgical and Medical Instrument Manufacturing |
SIC | 3842: Orthopedic, Prosthetic, and Surgical Appliances and Supplies |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
169,400
ft2
|
Annual Production | 200,000
pieces
|
Production Hrs. Annual | 2,082
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $202,000 | 2,371,596 |
kWh
|
$0.085 |
Electricity Demand | $42,982 | 7,224 |
kW-mo/yr
|
$5.95 |
Natural Gas | $11,792 | 1,318 |
MMBtu
|
$8.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $40,745 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,745 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7224: Reduce space conditioning during non-working hours | $29,000 | $6,930 |
$29,000
341,000
kWh
|
- | - | - | |
02 | 2.7124: Make a practice of turning off lights when not needed | $4,170 | - |
$4,170
49,100
kWh
|
- | - | - | |
03 | 2.7124: Make a practice of turning off lights when not needed | $3,020 | - |
$2,470
29,100
kWh
|
$550
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,200 | $1,420 |
$1,030
12,140
kWh
|
$100
-
kW-mo/yr
|
$455 | $615 | |
05 | 2.7124: Make a practice of turning off lights when not needed | $1,095 | - |
$765
9,000
kWh
|
$330
-
kW-mo/yr
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $830 | $375 |
$610
7,200
kWh
|
$220
-
kW-mo/yr
|
- | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $260 | $70 |
$180
2,120
kWh
|
$80
-
kW-mo/yr
|
- | - | |
08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $170 | $200 |
$120
1,420
kWh
|
$50
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $40,745 | $8,995 |
$38,345
451,080
kWh
|
$1,330
-
kW-mo/yr
|
$455 | $615 | ||
TOTAL IMPLEMENTED | $40,745 | $8,995 |
$38,345
451,080
kWh
|
$1,330
-
kW-mo/yr
|
$455 | $615 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs