Assessment Year | 2006 |
---|---|
Principal Product | Library furniture |
NAICS | 337127: Institutional Furniture Manufacturing |
SIC | 2531: Public Building and Related Furniture |
Sales Range | $5 M to 10M |
# of Employees | 100 |
Plant Area |
93,618
ft2
|
Annual Production | 21,600
pieces
|
Production Hrs. Annual | 3,233
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $53,724 | 550,272 |
kWh
|
$0.098 |
Electricity Demand | $30,684 | 3,336 |
kW-mo/yr
|
$9.20 |
Natural Gas | $22,628 | 2,722 |
MMBtu
|
$8.31 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $31,505 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $31,505 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $12,500 | $1,000 |
$10,470
103,700
kWh
|
$2,030
-
kW-mo/yr
|
- | - | |
02 | 2.5115: Reposition oven walls to reduce heated space | $11,700 | $500 |
$9,800
97,000
kWh
|
$1,900
-
kW-mo/yr
|
- | - | |
03 | 2.8123: Pay utility bills on time | $4,560 | - | - | - | - | $4,560 | |
04 | 2.7123: Keep lamps and reflectors clean | $1,810 | - |
$2,540
25,150
kWh
|
- | $(-730.0) | - | |
05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $390 | $6 |
$330
3,270
kWh
|
$60
-
kW-mo/yr
|
- | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $340 | - |
$340
3,370
kWh
|
- | - | - | |
07 | 2.4314: Use synthetic lubricant | $205 | - |
$170
1,710
kWh
|
$35
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $31,505 | $1,506 |
$23,650
234,200
kWh
|
$4,025
-
kW-mo/yr
|
$(-730.0) | $4,560 | ||
TOTAL IMPLEMENTED | $31,505 | $1,506 |
$23,650
234,200
kWh
|
$4,025
-
kW-mo/yr
|
$(-730.0) | $4,560 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs