| Assessment Year | 2006 |
|---|---|
| Principal Product | Industrial Maintenance Coatings |
| NAICS | 325998: All Other Miscellaneous Chemical Product and Preparation Manufacturing |
| SIC | 2851: Paints, Varnishes, Lacquers, Enamels, and Allied Products |
| Sales Range | $10 M to 50M |
| # of Employees | 60 |
| Plant Area |
20,000
ft2
|
| Annual Production | 915
Tgal
|
| Production Hrs. Annual | 3,960
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $52,840 | 439,854 |
kWh
|
$0.12 |
| Electricity Demand | $13,392 | 2,328 |
kW-mo/yr
|
$5.75 |
| Electricity Fees | $456 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $14,900 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,400 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 3.2176: Increase use of automation | $4,990 | - |
$(-230.0)
(-2,300)
kWh
|
$(-180.0)
-
kW-mo/yr
|
$5,400 | - | |
| 02 | 3.5217: Reuse / recycle/ sell paper products | $2,575 | $6,700 | - | - | - | $2,575 | |
| 03 | 2.3212: Optimize plant power factor | $2,200 | $6,200 | - |
$2,200
-
kW-mo/yr
|
- | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,600 | $250 |
$1,370
13,000
kWh
|
$230
-
kW-mo/yr
|
- | - | |
| 05 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $810 | - |
$810
7,750
kWh
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $810 | $245 |
$690
6,540
kWh
|
$120
-
kW-mo/yr
|
- | - | |
| 07 | 2.7145: Install skylights | $760 | $1,760 |
$760
7,240
kWh
|
- | - | - | |
| 08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $565 | $200 |
$130
1,230
kWh
|
$10
-
kW-mo/yr
|
- | $425 | |
| 09 | 2.7124: Make a practice of turning off lights when not needed | $440 | - |
$440
4,160
kWh
|
- | - | - | |
| 10 | 2.4314: Use synthetic lubricant | $150 | - |
$130
1,250
kWh
|
$20
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $14,900 | $15,355 |
$4,100
38,870
kWh
|
$2,400
-
kW-mo/yr
|
$5,400 | $3,000 | ||
| TOTAL IMPLEMENTED | $7,400 | $495 |
$1,830
17,240
kWh
|
$170
-
kW-mo/yr
|
$5,400 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs