Assessment Year | 2006 |
---|---|
Principal Product | Vinyl composition floor tiles |
NAICS | 327120: Clay Building Material and Refractories Manufacturing |
SIC | 3996: Linoleum, Asphalted-Felt-Base, and Other Hard Surface Floor Coverings, Not Elsewhere Classified |
Sales Range | $50 M to 100M |
# of Employees | 250 |
Plant Area |
432,000
ft2
|
Annual Production | 234,000,000
pieces
|
Production Hrs. Annual | 7,250
hrs
|
Location (State) | Texas |
View Case Study |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,795,900 | 36,020,375 |
kWh
|
$0.078 |
Electricity Demand | $521,497 | 78,840 |
kW-mo/yr
|
$6.61 |
Natural Gas | $1,443,660 | 156,888 |
MMBtu
|
$9.20 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $246,300 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $246,300 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4322: Use or replace with energy efficient substitutes | $113,000 | $1,300 | - | - |
$113,000
-
MMBtu
|
- | - | |
02 | 2.2121: Increase amount of condensate returned | $25,400 | $600 | - | - |
$25,400
-
MMBtu
|
- | - | |
03 | 2.2136: Install / repair insulation on steam lines | $21,460 | $60,000 | - | - |
$21,460
-
MMBtu
|
- | - | |
04 | 2.2113: Repair or replace steam traps | $21,100 | $1,235 | - | - |
$21,100
-
MMBtu
|
- | - | |
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $16,630 | - |
$11,500
135,800
kWh
|
$1,320
-
kW-mo/yr
|
- | - | $3,810 | |
06 | 2.4239: Eliminate or reduce compressed air usage | $13,470 | $390 |
$12,150
143,000
kWh
|
$1,320
-
kW-mo/yr
|
- | - | - | |
07 | 3.4154: Eliminate leaks in water lines and valves | $10,440 | $85 | - | - | - |
$10,440
-
Tgal
|
- | |
08 | 2.4314: Use synthetic lubricant | $8,900 | - |
$8,900
104,700
kWh
|
- | - | - | - | |
09 | 2.2135: Repair and eliminate steam leaks | $8,100 | $500 | - | - |
$8,100
-
MMBtu
|
- | - | |
10 | 2.7124: Make a practice of turning off lights when not needed | $7,800 | - |
$7,800
91,600
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $246,300 | $64,110 |
$40,350
475,100
kWh
|
$2,640
-
kW-mo/yr
|
$189,060
-
MMBtu
|
$10,440
-
Tgal
|
$3,810 | ||
TOTAL IMPLEMENTED | $246,300 | $64,110 |
$40,350
475,100
kWh
|
$2,640
-
kW-mo/yr
|
$189,060
-
MMBtu
|
$10,440
-
Tgal
|
$3,810 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs