ITAC Assessment: AM0516
ITAC logo
ITAC Assessment: AM0516
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Oil field specialty chemicals
NAICS 325180: Other Basic Inorganic Chemical Manufacturing
SIC 2819: Industrial Inorganic Chemicals, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 35
Plant Area 50,000
ft2
Annual Production 32,000,000
lb
Production Hrs. Annual 3,980
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $96,567 1,379,400
kWh
Electricity Demand $17,400 4,920
kW-mo/yr
Electricity Fees $55 -
Natural Gas $210,351 19,917
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $74,820 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $74,147

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $7,530 $500 - $7,530
-
MMBtu
- -
02 2.8121: Apply for tax-free status for energy purchases $31,494 $12,000 - - $6,294 $25,200
03 2.8121: Apply for tax-free status for energy purchases $30,123 $12,050 - - $6,023 $24,100
04 2.2135: Repair and eliminate steam leaks $4,570 $1,000 - $4,570
-
MMBtu
- -
05 2.8123: Pay utility bills on time $673 - - - $673 -
06 2.7124: Make a practice of turning off lights when not needed $430 - $430
8,470
kWh
- - -
TOTAL RECOMMENDED $74,820 $25,550 $430
8,470
kWh
$12,100
-
MMBtu
$12,990 $49,300
TOTAL IMPLEMENTED $74,147 $25,550 $430
8,470
kWh
$12,100
-
MMBtu
$12,317 $49,300
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs