ITAC Assessment: AM0514
ITAC logo
ITAC Assessment: AM0514
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Semiconductors
NAICS 334413: Semiconductor and Related Device Manufacturing
SIC 3674: Semiconductors and Related Devices
Sales Range greater than $500
M
# of Employees 1,500
Plant Area 1,000,000
ft2
Annual Production 438,000
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $8,631,919 164,686,000
kWh
Electricity Demand $716,290 245,545
kW-mo/yr
Electricity Fees $217,715 -
Natural Gas $1,077,636 132,106
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $233,427 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $204,125

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.1336: Install equipment to utilize waste fuel $189,400 $50,000 - - $89,400
-
MMBtu
$100,000
-
gal
-
02 2.4314: Use synthetic lubricant $27,782 - $25,818
320,725
kWh
$1,964
-
kW-mo/yr
- - -
03 2.1233: Analyze flue gas for proper air/fuel ratio $9,900 $500 - - $9,900
-
MMBtu
- -
04 2.7135: Install occupancy sensors $2,520 $790 $2,470
31,680
kWh
$50
-
kW-mo/yr
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $2,305 $1,450 $335
4,160
kWh
$25
-
kW-mo/yr
- - $1,945
06 2.2511: Insulate bare equipment $1,520 $100 - - $1,520
-
MMBtu
- -
TOTAL RECOMMENDED $233,427 $52,840 $28,623
356,565
kWh
$2,039
-
kW-mo/yr
$100,820
-
MMBtu
$100,000
-
gal
$1,945
TOTAL IMPLEMENTED $204,125 $52,740 $2,805
35,840
kWh
$75
-
kW-mo/yr
$99,300
-
MMBtu
$100,000
-
gal
$1,945
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs