| Assessment Year | 2006 |
|---|---|
| Principal Product | Horizontal, vertical, submersible pumps |
| NAICS | 333911: Pump and Pumping Equipment Manufacturing |
| SIC | 3561: Pumps and Pumping Equipment |
| Sales Range | $50 M to 100M |
| # of Employees | 220 |
| Plant Area |
140,000
ft2
|
| Annual Production | 1,300
pieces
|
| Production Hrs. Annual | 3,540
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $238,436 | 3,458,310 |
kWh
|
$0.069 |
| Electricity Demand | $120,120 | 22,902 |
kW-mo/yr
|
$5.24 |
| Electricity Fees | $9,693 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,675 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $59,625 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.8121: Apply for tax-free status for energy purchases | $48,200 | - | - | - | $48,200 | - | - | |
| 02 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $6,440 | - | - |
$6,440
-
kW-mo/yr
|
- | - | - | |
| 03 | 3.5311: Recover and reuse waste material | $6,200 | $9,135 | - | - | - | - | $6,200 | |
| 04 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,820 | - | - |
$4,820
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,965 | $860 |
$3,210
30,900
kWh
|
$755
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,020 | - |
$750
7,200
kWh
|
$270
-
kW-mo/yr
|
- | - | - | |
| 07 | 3.7132: Reuse rags until completely soiled | $1,300 | - | - | - | - | $1,300 | - | |
| 08 | 2.6218: Turn off equipment when not in use | $800 | - |
$800
7,600
kWh
|
- | - | - | - | |
| 09 | 2.4314: Use synthetic lubricant | $700 | - |
$700
6,615
kWh
|
- | - | - | - | |
| 10 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $230 | - |
$210
200
kWh
|
$20
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $73,675 | $9,995 |
$5,670
52,515
kWh
|
$12,305
-
kW-mo/yr
|
$48,200 | $1,300 | $6,200 | ||
| TOTAL IMPLEMENTED | $59,625 | $860 |
$3,960
38,100
kWh
|
$7,465
-
kW-mo/yr
|
$48,200 | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | Ancillary Material Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs