| Assessment Year | 2006 |
|---|---|
| Principal Product | Plug valves, pipeline closures |
| NAICS | 332919: Other Metal Valve and Pipe Fitting Manufacturing |
| SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
71,900
ft2
|
| Annual Production | 38,000
pieces
|
| Production Hrs. Annual | 5,781
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $106,607 | 1,807,104 |
kWh
|
$0.059 |
| Electricity Fees | $20,708 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $11,980 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,180 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,340 | $1,125 |
$2,900
49,100
kWh
|
- | - | $(-1,560.0) | |
| 02 | 4.211: Consider use / purchase of bulk materials where possible | $2,560 | $1,640 | - | $2,490 | - | $70 | |
| 03 | 2.8121: Apply for tax-free status for energy purchases | $2,270 | - | - | - | $2,270 | - | |
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,910 | $1,000 |
$1,910
32,000
kWh
|
- | - | - | |
| 05 | 2.7145: Install skylights | $1,170 | $2,140 |
$1,550
26,000
kWh
|
$(-380.0) | - | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $1,360 | $470 |
$1,360
22,750
kWh
|
- | - | - | |
| 07 | 2.4314: Use synthetic lubricant | $1,000 | - |
$1,000
17,250
kWh
|
- | - | - | |
| 08 | 2.7124: Make a practice of turning off lights when not needed | $370 | - |
$370
6,200
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $11,980 | $6,375 |
$9,090
153,300
kWh
|
$2,110 | $2,270 | $(-1,490.0) | ||
| TOTAL IMPLEMENTED | $4,180 | $1,000 |
$1,910
32,000
kWh
|
- | $2,270 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs