| Assessment Year | 2006 |
|---|---|
| Principal Product | Metal stampings |
| NAICS | 332119: Metal Crown, Closure, and Other Metal Stamping (except Automotive) |
| SIC | 3469: Metal Stampings, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 110 |
| Plant Area |
80,000
ft2
|
| Annual Production | 25,000,000
pieces
|
| Production Hrs. Annual | 4,700
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $106,484 | 3,167,520 |
kWh
|
$0.034 |
| Electricity Demand | $77,039 | 8,958 |
kW-mo/yr
|
$8.60 |
| Electricity Fees | $2,400 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,281 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $17,000 | $1,000 |
$15,200
220,000
kWh
|
$1,800
-
kW-mo/yr
|
- | - | |
| 02 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,400 | $7,650 | - | - | - | $2,400 | |
| 03 | 2.4314: Use synthetic lubricant | $1,155 | - |
$1,034
14,988
kWh
|
$121
-
kW-mo/yr
|
- | - | |
| 04 | 2.7124: Make a practice of turning off lights when not needed | $686 | - |
$620
8,960
kWh
|
$66
-
kW-mo/yr
|
- | - | |
| 05 | 3.5217: Reuse / recycle/ sell paper products | $455 | - | - | - |
$455
-
lb
|
- | |
| 06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $420 | - | - | - |
$420
-
lb
|
- | |
| 07 | 2.6212: Turn off equipment during breaks, reduce operating time | $165 | - |
$165
4,000
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $22,281 | $8,650 |
$17,019
247,948
kWh
|
$1,987
-
kW-mo/yr
|
$875
-
lb
|
$2,400 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs