Assessment Year | 2005 |
---|---|
Principal Product | Pressure relief valves |
NAICS | 332911: Industrial Valve Manufacturing |
SIC | 3491: Industrial Valves |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
50,000
ft2
|
Annual Production | 2,400
pieces
|
Production Hrs. Annual | 3,012
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $101,713 | 1,161,984 |
kWh
|
$0.088 |
Electricity Demand | $20,530 | 6,985 |
kW-mo/yr
|
$2.94 |
Electricity Fees | $484 | - |
|
- |
Natural Gas | $3,000 | 314 |
MMBtu
|
$9.55 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $9,975 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,187 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4239: Eliminate or reduce compressed air usage | $4,010 | $1,800 |
$4,010
63,600
kWh
|
- | - | - | |
02 | 2.8121: Apply for tax-free status for energy purchases | $2,212 | $992 | - | - | $228 | $1,984 | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,920 | $200 |
$1,800
28,500
kWh
|
$120
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $788 | $384 |
$154
2,450
kWh
|
$3
-
kW-mo/yr
|
$631 | - | |
05 | 2.7124: Make a practice of turning off lights when not needed | $665 | $225 |
$610
9,700
kWh
|
$55
-
kW-mo/yr
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $380 | $20 |
$360
5,680
kWh
|
$20
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $9,975 | $3,621 |
$6,934
109,930
kWh
|
$198
-
kW-mo/yr
|
$859 | $1,984 | ||
TOTAL IMPLEMENTED | $9,187 | $3,237 |
$6,780
107,480
kWh
|
$195
-
kW-mo/yr
|
$228 | $1,984 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs