ITAC Assessment: AM0457
ITAC logo
ITAC Assessment: AM0457
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Detention institution cell doors, locks, safes and hardware
NAICS 332321: Metal Window and Door Manufacturing
SIC 3442: Metal Doors, Sash, Frames, Molding, and Trim Manufacturing
Sales Range $10
M
to 50
M
# of Employees 190
Plant Area 150,000
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 3,920
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $79,967 1,938,848
kWh
Electricity Demand $28,559 4,182
kW-mo/yr
Electricity Fees $11,501 -
Natural Gas $115,097 13,408
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $92,975 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,575

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,750 $21 $2,090
34,450
kWh
$660
-
kW-mo/yr
- - - -
02 2.4235: Remove or close off unneeded compressed air lines $1,360 $4,370 $1,360
22,400
kWh
- - - - -
03 2.4239: Eliminate or reduce compressed air usage $1,270 $120 $1,270
21,000
kWh
- - - - -
04 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $790 $500 $600
9,930
kWh
$190
-
kW-mo/yr
- - - -
05 2.6212: Turn off equipment during breaks, reduce operating time $265 $130 $195
3,230
kWh
$70
-
kW-mo/yr
- - - -
06 2.7124: Make a practice of turning off lights when not needed $230 - $230
3,740
kWh
- - - - -
07 2.8121: Apply for tax-free status for energy purchases $84,400 $8,800 - - $17,600 - - $66,800
08 2.7124: Make a practice of turning off lights when not needed $1,910 $880 $395
5,600
kWh
$50
-
kW-mo/yr
- $940 $525 -
TOTAL RECOMMENDED $92,975 $14,821 $6,140
100,350
kWh
$970
-
kW-mo/yr
$17,600 $940 $525 $66,800
TOTAL IMPLEMENTED $8,575 $6,021 $6,140
100,350
kWh
$970
-
kW-mo/yr
- $940 $525 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Personnel Changes Savings Primary Raw Material Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs