Assessment Year | 2003 |
---|---|
Principal Product | Electrical connectors |
NAICS | 334417: Electronic Connector Manufacturing |
SIC | 3643: Current-Carrying Wiring Devices |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
63,000
ft2
|
Annual Production | 910,000
pieces
|
Production Hrs. Annual | 2,832
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $171,210 | 2,561,040 |
kWh
|
$0.067 |
Electricity Demand | $24,977 | 8,885 |
kW-mo/yr
|
$2.81 |
Electricity Fees | $212 | - |
|
- |
Natural Gas | $1,424 | 259 |
MMBtu
|
$5.50 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $32,795 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,975 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $17,500 | $22,850 | n/a | - |
$17,500
-
kW-mo/yr
|
- |
02 | 2.7229: Air condition only space necessary | $9,640 | $190 |
$7,690
142,400
kWh
|
$1,950
-
kW-mo/yr
|
- | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,150 | $200 |
$2,150
39,700
kWh
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $530 | $830 |
$330
6,140
kWh
|
$200
-
kW-mo/yr
|
- | |
05 | 2.2511: Insulate bare equipment | $320 | $100 |
$320
6,000
kWh
|
- | - | |
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,655 | $560 |
$330
6,150
kWh
|
$65
-
kW-mo/yr
|
$2,260 | |
TOTAL RECOMMENDED | $32,795 | $24,730 |
$10,820
200,390
kWh
|
$19,715
-
kW-mo/yr
|
$2,260 | ||
TOTAL IMPLEMENTED | $14,975 | $1,780 |
$10,500
194,390
kWh
|
$2,215
-
kW-mo/yr
|
$2,260 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs