Assessment Year | 2003 |
---|---|
Principal Product | Industrial valve actuators |
NAICS | 333995: Fluid Power Cylinder and Actuator Manufacturing |
SIC | 3593: Fluid Power Cylinders and Actuators |
Sales Range | $10 M to 50M |
# of Employees | 180 |
Plant Area |
146,000
ft2
|
Annual Production | 16,545
pieces
|
Production Hrs. Annual | 5,980
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $259,431 | 5,781,214 |
kWh
|
$0.045 |
Electricity Demand | $42,999 | 7,026 |
kW-mo/yr
|
$6.12 |
Electricity Fees | $40,380 | - |
|
- |
Natural Gas | $39,891 | 4,650 |
MMBtu
|
$8.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $23,773 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $19,763 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $5,150 | $500 |
$5,150
126,900
kWh
|
- | - | - | |
02 | 3.7132: Reuse rags until completely soiled | $4,500 | - | - | - | $4,500 | - | |
03 | 3.2123: Convert to high volume low pressure (hvlp) paint guns | $4,010 | $340 | - | - | $4,010 | - | |
04 | 2.8121: Apply for tax-free status for energy purchases | $7,553 | $800 | - | $1,553 | - | $6,000 | |
05 | 4.211: Consider use / purchase of bulk materials where possible | $1,490 | $2,880 | - | $1,490 | - | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $830 | $42 |
$830
20,400
kWh
|
- | - | - | |
07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $240 | $145 |
$95
2,330
kWh
|
$145 | - | - | |
TOTAL RECOMMENDED | $23,773 | $4,707 |
$6,075
149,630
kWh
|
$3,188 | $8,510 | $6,000 | ||
TOTAL IMPLEMENTED | $19,763 | $4,367 |
$6,075
149,630
kWh
|
$3,188 | $4,500 | $6,000 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Personnel Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs