Assessment Year | 2003 |
---|---|
Principal Product | Lime processing |
NAICS | 327410: Lime Manufacturing |
SIC | 3274: Lime |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 400,000
ton
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,053,076 | 24,791,400 |
kWh
|
$0.042 |
Electricity Demand | $15,942 | 29,952 |
kW-mo/yr
|
$0.53 |
Natural Gas | $4,063,260 | 1,054,610 |
MMBtu
|
$3.85 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $19,800 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $15,620 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|
01 | 4.652: Replace existing equipment with more suitable substitutes | $13,600 | $4,000 | - | $13,600 | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,180 | $500 |
$4,180
110,000
kWh
|
- | |
03 | 2.7124: Make a practice of turning off lights when not needed | $2,020 | - |
$2,020
53,270
kWh
|
- | |
TOTAL RECOMMENDED | $19,800 | $4,500 |
$6,200
163,270
kWh
|
$13,600 | ||
TOTAL IMPLEMENTED | $15,620 | $4,000 |
$2,020
53,270
kWh
|
$13,600 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs