Assessment Year | 2002 |
---|---|
Principal Product | Refined petroleum products, sulfur |
NAICS | 324110: Petroleum Refineries |
SIC | 2911: Petroleum Refining |
Sales Range | greater than $500 M |
# of Employees | 325 |
Plant Area |
n/a
|
Annual Production | 42,000,000
bbl
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,512,297 | 41,194,817 |
kWh
|
$0.061 |
Natural Gas | $43,870,282 | 10,982,620 |
MMBtu
|
$3.99 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $3,726,571 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,898,771 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|
01 | 3.1191: Change procedures / equipment / operating conditions | $1 | - | - | - | - | - | $1 | - | - | |
02 | 2.1221: Replace obsolete burners with more efficient ones | $189,000 | $1,540,000 | n/a | - |
$189,000
-
MMBtu
|
- | - | - | - | - |
03 | 2.4323: Use optimum size and capacity equipment | $1,809,500 | $25,000 | - | - |
$1,311,800
-
MMBtu
|
- | - | - | $497,700 | |
04 | 2.2113: Repair or replace steam traps | $703,100 | $9,000 | - |
$703,100
-
MMBtu
|
- | - | - | - | - | |
05 | 2.1336: Install equipment to utilize waste fuel | $491,300 | $60,000 | - |
$491,300
-
MMBtu
|
- | - | - | - | - | |
06 | 2.2135: Repair and eliminate steam leaks | $284,250 | $13,200 | - |
$284,250
-
MMBtu
|
- | - | - | - | - | |
07 | 4.632: Change operating conditions | $133,100 | $249,000 | - | - |
$133,600
-
MMBtu
|
- | - | - | $(-500.0) | |
08 | 2.6125: Keep equipment clean | $34,560 | $10,000 |
$34,560
1,080,000
kWh
|
- | - | - | - | - | - | |
09 | 4.131: Modify process to reduce material use/cost | $27,800 | $18,880 | - | - | - | $27,800 | - | - | - | |
10 | 4.131: Modify process to reduce material use/cost | $18,500 | $15,780 | - | - | - | $18,500 | - | - | - | |
11 | 4.212: Adopt in-house material generation | $14,400 | - | - | - | - | - | - |
$14,400
-
Tgal
|
- | |
12 | 2.4314: Use synthetic lubricant | $9,100 | - |
$9,100
284,000
kWh
|
- | - | - | - | - | - | |
13 | 2.2136: Install / repair insulation on steam lines | $6,380 | $9,470 | - |
$6,380
-
MMBtu
|
- | - | - | - | - | |
14 | 2.7124: Make a practice of turning off lights when not needed | $5,580 | - |
$5,580
174,500
kWh
|
- | - | - | - | - | - | |
TOTAL RECOMMENDED | $3,726,571 | $1,950,330 |
$49,240
1,538,500
kWh
|
$1,674,030
-
MMBtu
|
$1,445,400
-
MMBtu
|
$46,300 | $1 |
$14,400
-
Tgal
|
$497,200 | ||
TOTAL IMPLEMENTED | $2,898,771 | $101,330 |
$49,240
1,538,500
kWh
|
$993,730
-
MMBtu
|
$1,311,800
-
MMBtu
|
$46,300 | $1 | - | $497,700 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Other Gas Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs