ITAC Assessment: AM0409
ITAC logo
ITAC Assessment: AM0409
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Abrasive blasting and recovery equipment
NAICS
n/a
SIC 3559: Special Industry Machinery, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 56
Plant Area 85,000
ft2
Annual Production 4,200
pieces
Production Hrs. Annual 2,068
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $73,809 1,025,856
kWh
Electricity Demand $19,725 6,483
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,853 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,493

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.3212: Optimize plant power factor $10,660 $15,375 - $10,660
-
kW-mo/yr
- - -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $5,870 $12,210 $5,870
83,700
kWh
- - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $2,120 $6,440 $1,630
23,320
kWh
$490
-
kW-mo/yr
- - -
04 3.7132: Reuse rags until completely soiled $1,850 - - - $1,850
-
lb
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,600 $800 $1,600
22,800
kWh
- - - -
06 2.7124: Make a practice of turning off lights when not needed $1,140 - $1,140
16,300
kWh
- - - -
07 2.4231: Reduce the pressure of compressed air to the minimum required $840 $170 $840
12,000
kWh
- - - -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $800 $300 $140
2,000
kWh
$15
-
kW-mo/yr
- $645 -
09 4.211: Consider use / purchase of bulk materials where possible $720 - - - - - $720
10 4.821: Pay bills on time to avoid late fees $253 - - - - $253 -
TOTAL RECOMMENDED $25,853 $35,295 $11,220
160,120
kWh
$11,165
-
kW-mo/yr
$1,850
-
lb
$898 $720
TOTAL IMPLEMENTED $23,493 $34,825 $10,240
146,120
kWh
$11,150
-
kW-mo/yr
$1,850
-
lb
$253 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs