Assessment Year | 2002 |
---|---|
Principal Product | Abrasive blasting and recovery equipment |
NAICS |
n/a
|
SIC | 3559: Special Industry Machinery, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 56 |
Plant Area |
85,000
ft2
|
Annual Production | 4,200
pieces
|
Production Hrs. Annual | 2,068
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $73,809 | 1,025,856 |
kWh
|
$0.072 |
Electricity Demand | $19,725 | 6,483 |
kW-mo/yr
|
$3.04 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $25,853 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $23,493 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.3212: Optimize plant power factor | $10,660 | $15,375 | - |
$10,660
-
kW-mo/yr
|
- | - | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $5,870 | $12,210 |
$5,870
83,700
kWh
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,120 | $6,440 |
$1,630
23,320
kWh
|
$490
-
kW-mo/yr
|
- | - | - | |
04 | 3.7132: Reuse rags until completely soiled | $1,850 | - | - | - |
$1,850
-
lb
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,600 | $800 |
$1,600
22,800
kWh
|
- | - | - | - | |
06 | 2.7124: Make a practice of turning off lights when not needed | $1,140 | - |
$1,140
16,300
kWh
|
- | - | - | - | |
07 | 2.4231: Reduce the pressure of compressed air to the minimum required | $840 | $170 |
$840
12,000
kWh
|
- | - | - | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $800 | $300 |
$140
2,000
kWh
|
$15
-
kW-mo/yr
|
- | $645 | - | |
09 | 4.211: Consider use / purchase of bulk materials where possible | $720 | - | - | - | - | - | $720 | |
10 | 4.821: Pay bills on time to avoid late fees | $253 | - | - | - | - | $253 | - | |
TOTAL RECOMMENDED | $25,853 | $35,295 |
$11,220
160,120
kWh
|
$11,165
-
kW-mo/yr
|
$1,850
-
lb
|
$898 | $720 | ||
TOTAL IMPLEMENTED | $23,493 | $34,825 |
$10,240
146,120
kWh
|
$11,150
-
kW-mo/yr
|
$1,850
-
lb
|
$253 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs