Assessment Year | 2001 |
---|---|
Principal Product | Cresylic acid |
NAICS |
n/a
|
SIC | 2865: Cyclic Organic Crudes and Intermediates, and Organic Dyes and Pigments |
Sales Range | $50 M to 100M |
# of Employees | 110 |
Plant Area |
n/a
|
Annual Production | 16,000,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,325,644 | 31,223,517 |
kWh
|
$0.042 |
Electricity Demand | $295,771 | 47,841 |
kW-mo/yr
|
$6.18 |
Electricity Fees | $5,800 | - |
|
- |
Natural Gas | $8,866,936 | 1,485,366 |
MMBtu
|
$5.97 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,052,780 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $695,235 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2113: Repair or replace steam traps | $632,000 | $1,210 | - | - | - |
$632,000
-
MMBtu
|
- | |
02 | 2.3415: Use a fossil fuel engine to cogenerate electricity or motive power; and utilize heat | $248,500 | $1,730,000 |
$495,000
10,100,000
kWh
|
$14,700
-
kW-mo/yr
|
$(-54,200.0) |
$(-207,000.0)
-
MMBtu
|
- | |
03 | 2.2121: Increase amount of condensate returned | $61,175 | $15,000 | n/a | - | - | - |
$57,075
-
MMBtu
|
$4,100
-
Tgal
|
04 | 2.2135: Repair and eliminate steam leaks | $27,400 | $1,000 | - | - | - |
$27,400
-
MMBtu
|
- | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $26,070 | $53,700 | n/a |
$19,270
393,200
kWh
|
$6,800
-
kW-mo/yr
|
- | - | - |
06 | 2.2511: Insulate bare equipment | $19,300 | $865 | - | - | - |
$19,300
-
MMBtu
|
- | |
07 | 2.4314: Use synthetic lubricant | $11,100 | - |
$8,300
170,000
kWh
|
$2,800
-
kW-mo/yr
|
- | - | - | |
08 | 2.4133: Use most efficient type of electric motors | $10,700 | $3,300 |
$8,000
163,300
kWh
|
$2,700
-
kW-mo/yr
|
- | - | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $8,200 | - |
$3,300
67,700
kWh
|
$4,900
-
kW-mo/yr
|
- | - | - | |
10 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $4,325 | - | - |
$4,325
-
kW-mo/yr
|
- | - | - | |
11 | 2.7124: Make a practice of turning off lights when not needed | $4,010 | - |
$2,210
42,100
kWh
|
$1,800
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $1,052,780 | $1,805,075 |
$536,080
10,936,300
kWh
|
$38,025
-
kW-mo/yr
|
$(-54,200.0) |
$528,775
-
MMBtu
|
$4,100
-
Tgal
|
||
TOTAL IMPLEMENTED | $695,235 | $3,075 |
$5,510
109,800
kWh
|
$11,025
-
kW-mo/yr
|
- |
$678,700
-
MMBtu
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs