Assessment Year | 2001 |
---|---|
Principal Product | White portland cement |
NAICS |
n/a
|
SIC | 3241: Cement, Hydraulic |
Sales Range | $10 M to 50M |
# of Employees | 70 |
Plant Area |
n/a
|
Annual Production | 115,000
ton
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $537,579 | 22,988,793 |
kWh
|
$0.023 |
Electricity Demand | $165,459 | 40,740 |
kW-mo/yr
|
$4.06 |
Electricity Fees | $5,213 | - |
|
- |
Natural Gas | $1,262,872 | 477,204 |
MMBtu
|
$2.65 |
Other Energy | $868,001 | 910,000 |
MMBtu
|
$0.95 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $128,930 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,810 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.6218: Turn off equipment when not in use | $124,120 | - |
$6,120
221,000
kWh
|
- | - |
$118,000
-
Tgal
|
|
02 | 2.6218: Turn off equipment when not in use | $1,720 | - |
$490
17,300
kWh
|
- |
$1,230
-
MMBtu
|
- | |
03 | 2.4133: Use most efficient type of electric motors | $1,150 | $2,750 |
$990
35,350
kWh
|
$160
-
kW-mo/yr
|
- | - | |
04 | 2.7124: Make a practice of turning off lights when not needed | $1,040 | $960 |
$680
24,240
kWh
|
$360
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $900 | $200 |
$900
31,700
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $128,930 | $3,910 |
$9,180
329,590
kWh
|
$520
-
kW-mo/yr
|
$1,230
-
MMBtu
|
$118,000
-
Tgal
|
||
TOTAL IMPLEMENTED | $4,810 | $3,910 |
$3,060
108,590
kWh
|
$520
-
kW-mo/yr
|
$1,230
-
MMBtu
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs