ITAC Assessment: AM0399
ITAC logo
ITAC Assessment: AM0399
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Fiberglass storage tanks, fiberglass pipe and duct
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 94,000
ft2
Annual Production 1,350
pieces
Production Hrs. Annual 2,857
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $33,375 632,205
kWh
Electricity Demand $20,109 2,789
kW-mo/yr
Electricity Fees $494 -
Natural Gas $310 24
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $299,850 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $8,420

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
01 4.132: Purchase new equipment to reduce material use / cost $183,100 $150,000 - - $89,300
-
lb
$34,300 $59,500
02 4.132: Purchase new equipment to reduce material use / cost $107,750 $120,000 - - $77,750
-
lb
$30,000 -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,900 $1,000 $5,900
141,500
kWh
- - - -
04 2.4133: Use most efficient type of electric motors $800 $1,280 $400
9,600
kWh
$400
-
kW-mo/yr
- - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $600 $755 $600
14,100
kWh
- - - -
06 2.7123: Keep lamps and reflectors clean $510 $290 $510
16,900
kWh
- - - -
07 2.4314: Use synthetic lubricant $380 - $190
4,587
kWh
$190
-
kW-mo/yr
- - -
08 2.7121: Utilize daylight whenever possible in lieu of artificial light $310 - $310
10,220
kWh
- - - -
09 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $300 $100 $300
5,800
kWh
- - - -
10 3.7198: Reduce / eliminate use of disposable product $200 $175 - - $200
-
lb
- -
TOTAL RECOMMENDED $299,850 $273,600 $8,210
202,707
kWh
$590
-
kW-mo/yr
$167,250
-
lb
$64,300 $59,500
TOTAL IMPLEMENTED $8,420 $3,425 $8,020
198,120
kWh
$400
-
kW-mo/yr
- - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs