Assessment Year | 2001 |
---|---|
Principal Product | Oriented strand board |
NAICS |
n/a
|
SIC | 2493: Reconstituted Wood Products |
Sales Range | $50 M to 100M |
# of Employees | 150 |
Plant Area |
213,000
ft2
|
Annual Production | 310,000
thousand feet
|
Production Hrs. Annual | 8,448
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,687,352 | 73,062,000 |
kWh
|
$0.037 |
Electricity Demand | $852,823 | 128,190 |
kW-mo/yr
|
$6.65 |
Natural Gas | $2,233,929 | 600,637 |
MMBtu
|
$3.72 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $162,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $68,600 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $67,500 | $1,500 | - | - |
$67,500
-
MMBtu
|
- | - | |
02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $24,500 | - | - | - | - | - |
$24,500
-
lb
|
|
03 | 2.3212: Optimize plant power factor | $20,000 | $60,000 | - |
$20,000
-
kW-mo/yr
|
- | - | - | |
04 | 3.6192: Use a less expensive method of waste removal | $18,400 | - | - | - | - | - |
$18,400
-
lb
|
|
05 | 2.4314: Use synthetic lubricant | $13,950 | - |
$11,250
268,000
kWh
|
$2,700
-
kW-mo/yr
|
- | - | - | |
06 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $11,700 | $1,400 | - | - | - | - |
$11,700
-
lb
|
|
07 | 2.7124: Make a practice of turning off lights when not needed | $5,700 | - |
$3,800
90,000
kWh
|
$1,900
-
kW-mo/yr
|
- | - | - | |
08 | 3.6194: Ship hydraulic oil to secondary fuel program | $600 | - | - | - | - |
$600
-
gal
|
- | |
TOTAL RECOMMENDED | $162,350 | $62,900 |
$15,050
358,000
kWh
|
$24,600
-
kW-mo/yr
|
$67,500
-
MMBtu
|
$600
-
gal
|
$54,600
-
lb
|
||
TOTAL IMPLEMENTED | $68,600 | $60,000 |
$3,800
90,000
kWh
|
$21,900
-
kW-mo/yr
|
- | - |
$42,900
-
lb
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs