| Assessment Year | 2000 |
|---|---|
| Principal Product | machine shop products, parts for aircraft |
| NAICS |
n/a
|
| SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
| Sales Range | $1 M to 5M |
| # of Employees | 35 |
| Plant Area |
150,000
ft2
|
| Annual Production | 86,000
pieces
|
| Production Hrs. Annual | 2,932
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $62,704 | 1,587,339 |
kWh
|
$0.040 |
| Electricity Demand | $46,062 | 6,024 |
kW-mo/yr
|
$7.65 |
| Electricity Fees | $672 | - |
|
- |
| Natural Gas | $6,914 | 1,274 |
MMBtu
|
$5.43 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $18,746 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $8,554 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.652: Replace existing equipment with more suitable substitutes | $9,200 | $1,000 | - | - | - | $9,200 | - | - | - | |
| 02 | 2.8112: Combine utility meters | $3,644 | $8,000 | - |
$3,140
-
kW-mo/yr
|
$504 | - | - | - | - | |
| 03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,800 | $50 |
$1,800
39,859
kWh
|
- | - | - | - | - | - | |
| 04 | 2.8118: Check for accuracy of utility / power meters | $1,798 | - | - | - | - | - | - | - | $1,798 | |
| 05 | 2.8121: Apply for tax-free status for energy purchases | $527 | $800 | - | - | - | - | $527 | - | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $520 | $25 |
$300
6,741
kWh
|
$220
-
kW-mo/yr
|
- | - | - | - | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $600 | $1,000 |
$280
6,155
kWh
|
$320
-
kW-mo/yr
|
- | - | - | - | - | |
| 08 | 3.1161: Eliminate/reduce an operation | $392 | - | - | - | - | - | - | $392 | - | |
| 09 | 2.7124: Make a practice of turning off lights when not needed | $265 | - |
$150
3,224
kWh
|
$115
-
kW-mo/yr
|
- | - | - | - | - | |
| TOTAL RECOMMENDED | $18,746 | $10,875 |
$2,530
55,979
kWh
|
$3,795
-
kW-mo/yr
|
$504 | $9,200 | $527 | $392 | $1,798 | ||
| TOTAL IMPLEMENTED | $8,554 | $8,875 |
$2,250
49,824
kWh
|
$3,475
-
kW-mo/yr
|
$504 | - | $527 | - | $1,798 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs