Assessment Year | 2000 |
---|---|
Principal Product | Critical service pipe connectors, closures and metal flanges |
NAICS |
n/a
|
SIC | 3494: Valves and Pipe Fittings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 45 |
Plant Area |
12,000
ft2
|
Annual Production | 144,000
lb
|
Production Hrs. Annual | 6,600
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $35,365 | 660,023 |
kWh
|
$0.054 |
Electricity Demand | $5,158 | 1,784 |
kW-mo/yr
|
$2.89 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $81,450 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $80,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $75,370 | - | - | - |
$75,370
-
lb
|
- | |
02 | 2.3212: Optimize plant power factor | $1,650 | $2,100 | - |
$1,650
-
kW-mo/yr
|
- | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $1,300 | $590 |
$375
14,947
kWh
|
$925
-
kW-mo/yr
|
- | - | |
04 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,070 | $16 |
$500
19,930
kWh
|
$570
-
kW-mo/yr
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $930 | $200 |
$930
37,222
kWh
|
- | - | - | |
06 | 2.4322: Use or replace with energy efficient substitutes | $710 | $2,350 |
$710
28,136
kWh
|
- | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $320 | - |
$110
4,396
kWh
|
$210
-
kW-mo/yr
|
- | - | |
08 | 4.821: Pay bills on time to avoid late fees | $100 | - | - | - | - | $100 | |
TOTAL RECOMMENDED | $81,450 | $5,256 |
$2,625
104,631
kWh
|
$3,355
-
kW-mo/yr
|
$75,370
-
lb
|
$100 | ||
TOTAL IMPLEMENTED | $80,150 | $4,666 |
$2,250
89,684
kWh
|
$2,430
-
kW-mo/yr
|
$75,370
-
lb
|
$100 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs