ITAC Assessment: AM0372
ITAC logo
ITAC Assessment: AM0372
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product high density polyethylene barrels and containers
NAICS
n/a
SIC 3432: Plumbing Fixture Fittings and Trim
Sales Range $10
M
to 50
M
# of Employees 60
Plant Area 90,000
ft2
Annual Production 6,000,000
pieces
Production Hrs. Annual 8,520
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $304,608 8,492,087
kWh
Electricity Demand $143,505 20,458
kW-mo/yr
Natural Gas $1,419 295
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,502 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $23,262

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
01 2.6218: Turn off equipment when not in use $6,100 - $3,650
126,026
kWh
$2,450
-
kW-mo/yr
- -
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $5,700 $500 $5,700
196,366
kWh
- - -
03 3.5248: Separate and recycle scrap metal to foundry or for sale $3,850 - - - - $3,850
04 2.7142: Utilize higher efficiency lamps and/or ballasts $3,065 $210 $2,260
77,960
kWh
$805
-
kW-mo/yr
- -
05 3.6192: Use a less expensive method of waste removal $2,592 $150 - - $2,592
-
lb
-
06 2.7145: Install skylights $1,300 $5,520 $1,300
45,135
kWh
- - -
07 2.2515: Use optimum thickness insulation $940 $734 $690
24,033
kWh
$250
-
kW-mo/yr
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $585 - $435
14,947
kWh
$150
-
kW-mo/yr
- -
09 2.7124: Make a practice of turning off lights when not needed $585 - $585
20,223
kWh
- - -
10 2.7135: Install occupancy sensors $470 $210 $470
16,413
kWh
- - -
11 3.7212: Improved material handling (mixing and transfer) $315 - - - $315
-
lb
-
TOTAL RECOMMENDED $25,502 $7,324 $15,090
521,103
kWh
$3,655
-
kW-mo/yr
$2,907
-
lb
$3,850
TOTAL IMPLEMENTED $23,262 $1,070 $13,100
451,935
kWh
$3,405
-
kW-mo/yr
$2,907
-
lb
$3,850
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs