ITAC Assessment: AM0363
ITAC logo
ITAC Assessment: AM0363
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Refrigeration and other control valves
NAICS
n/a
SIC 3491: Industrial Valves
Sales Range $10
M
to 50
M
# of Employees 215
Plant Area 50,000
ft2
Annual Production 1,750,000
lb
Production Hrs. Annual 5,072
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $91,765 1,987,397
kWh
Electricity Demand $17,641 5,428
kW-mo/yr
Natural Gas $6,019 1,439
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,535 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,255

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings
01 3.7191: Use water based spray abrasives instead of bar abrasives $13,500 $70,000 - - $13,500
-
gal
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $4,540 $500 $4,540
105,510
kWh
- - -
03 2.2511: Insulate bare equipment $1,245 $210 $1,000
23,154
kWh
$245
-
kW-mo/yr
- -
04 2.7135: Install occupancy sensors $600 $180 $600
13,775
kWh
- - -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $470 $215 $60
1,465
kWh
$10
-
kW-mo/yr
- $400
06 2.4314: Use synthetic lubricant $180 - $145
3,224
kWh
$35
-
kW-mo/yr
- -
TOTAL RECOMMENDED $20,535 $71,105 $6,345
147,128
kWh
$290
-
kW-mo/yr
$13,500
-
gal
$400
TOTAL IMPLEMENTED $6,255 $925 $5,600
130,129
kWh
$255
-
kW-mo/yr
- $400
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs