ITAC Assessment: AM0356
ITAC logo
ITAC Assessment: AM0356
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product fabricated steel parts
NAICS
n/a
SIC 3444: Sheet Metal Work
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 94,000
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 4,348
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $92,711 1,816,237
kWh
Electricity Demand $9,043 7,337
kW-mo/yr
Natural Gas $7,930 1,862
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $62,495 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,555

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings
01 3.2123: Convert to high volume low pressure (hvlp) paint guns $24,660 - - - $24,660
-
gal
-
02 2.3131: Reschedule plant operations or reduce load to avoid peaks $12,500 - - $12,500
-
kW-mo/yr
- -
03 3.5316: Contract a wood pallet recycling company $8,260 - - - - $8,260
-
lb
04 2.3212: Optimize plant power factor $5,710 $18,100 - $5,710
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,570 $1,500 $3,570
111,665
kWh
- - -
06 3.5315: Lease / purchase baler; sell cardboard to recycler $2,790 $5,000 - - - $2,790
-
lb
07 2.7134: Use photocell controls $1,960 $150 $1,030
35,463
kWh
$930
-
kW-mo/yr
- -
08 2.3212: Optimize plant power factor $1,950 $5,500 - $1,950
-
kW-mo/yr
- -
09 2.6212: Turn off equipment during breaks, reduce operating time $730 - $730
22,860
kWh
- - -
10 2.7142: Utilize higher efficiency lamps and/or ballasts $365 $940 $175
5,569
kWh
$190
-
kW-mo/yr
- -
TOTAL RECOMMENDED $62,495 $31,190 $5,505
175,557
kWh
$21,280
-
kW-mo/yr
$24,660
-
gal
$11,050
-
lb
TOTAL IMPLEMENTED $13,555 $26,190 $4,775
152,697
kWh
$8,780
-
kW-mo/yr
- -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs