| Assessment Year | 1998 |
|---|---|
| Principal Product | Rockwool insulation |
| NAICS |
n/a
|
| SIC | 3296: Mineral Wool |
| Sales Range | $10 M to 50M |
| # of Employees | 92 |
| Plant Area |
22,530
ft2
|
| Annual Production | 100,000,000
lb
|
| Production Hrs. Annual | 7,488
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $469,322 | 19,418,816 |
kWh
|
$0.024 |
| Electricity Demand | $190,178 | 25,640 |
kW-mo/yr
|
$7.42 |
| Electricity Fees | $275 | - |
|
- |
| Other Energy | $2,080,000 | 406,080 |
MMBtu
|
$5.12 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $74,150 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $71,410 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 4.423: Move product using mechanical means | $57,200 | $13,700 | - | - | - | - | - | $57,200 | |
| 02 | 3.7311: Maintain machines to reduce leaks | $8,010 | $630 | - | - | - |
$8,010
-
gal
|
- | - | |
| 03 | 2.4314: Use synthetic lubricant | $2,840 | - |
$1,520
63,599
kWh
|
$1,320
-
kW-mo/yr
|
- | - | - | - | |
| 04 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $2,740 | - | - | - | - | - |
$2,740
-
lb
|
- | |
| 05 | 2.7124: Make a practice of turning off lights when not needed | $1,600 | $200 |
$510
21,102
kWh
|
$1,090
-
kW-mo/yr
|
- | - | - | - | |
| 06 | 2.4133: Use most efficient type of electric motors | $1,100 | $2,290 |
$580
24,326
kWh
|
$520
-
kW-mo/yr
|
- | - | - | - | |
| 07 | 3.4111: Use closed cycle process to minimize waste water production | $460 | $2,150 |
$(-25.0)
(-1,172)
kWh
|
$(-65.0)
-
kW-mo/yr
|
$550
-
Tgal
|
- | - | - | |
| 08 | 2.7124: Make a practice of turning off lights when not needed | $200 | $60 |
$80
3,224
kWh
|
$120
-
kW-mo/yr
|
- | - | - | - | |
| TOTAL RECOMMENDED | $74,150 | $19,030 |
$2,665
111,079
kWh
|
$2,985
-
kW-mo/yr
|
$550
-
Tgal
|
$8,010
-
gal
|
$2,740
-
lb
|
$57,200 | ||
| TOTAL IMPLEMENTED | $71,410 | $19,030 |
$2,665
111,079
kWh
|
$2,985
-
kW-mo/yr
|
$550
-
Tgal
|
$8,010
-
gal
|
- | $57,200 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs