ITAC Assessment: AM0311
ITAC logo
ITAC Assessment: AM0311
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Milk, ice cream
NAICS
n/a
SIC 2026: Fluid Milk
Sales Range $10
M
to 50
M
# of Employees 120
Plant Area 42,000
ft2
Annual Production 21,600
Tgal
Production Hrs. Annual 5,900
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $153,687 8,499,414
kWh
Electricity Demand $265,913 19,768
kW-mo/yr
Electricity Fees $3,865 -
Natural Gas $110,140 26,300
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $193,536 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $49,011

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 3.6113: Remove sludge from tanks on a regular basis $116,000 $900,000 - - - $116,000
-
Tgal
- - -
02 2.8118: Check for accuracy of utility / power meters $31,316 - - $31,316
-
kW-mo/yr
- - - - -
03 3.1291: Eliminate practice of mixing waste streams $23,800 $1,515 - - - - $23,800
-
gal
- -
04 2.7134: Use photocell controls $11,300 $340 $11,300
348,769
kWh
- - - - - -
05 2.4314: Use synthetic lubricant $2,785 - $1,665
51,583
kWh
$1,120
-
kW-mo/yr
- - - - -
06 3.5212: Regrind, reuse, or sell scrap plastic parts $2,170 - - - - - - $2,170
-
lb
-
07 3.4154: Eliminate leaks in water lines and valves $1,620 $1,010 - - $460
-
MMBtu
$1,160
-
Tgal
- - -
08 2.4133: Use most efficient type of electric motors $1,500 $2,100 $920
28,429
kWh
$580
-
kW-mo/yr
- - - - -
09 2.7124: Make a practice of turning off lights when not needed $1,400 - $985
30,481
kWh
$415
-
kW-mo/yr
- - - - -
10 4.652: Replace existing equipment with more suitable substitutes $1,105 $1,205 $220
6,741
kWh
$120
-
kW-mo/yr
- - - - $765
11 2.7111: Reduce illumination to minimum necessary levels $290 $93 $160
4,982
kWh
$130
-
kW-mo/yr
- - - - -
12 2.7135: Install occupancy sensors $250 $485 $250
7,913
kWh
- - - - - -
TOTAL RECOMMENDED $193,536 $906,748 $15,500
478,898
kWh
$33,681
-
kW-mo/yr
$460
-
MMBtu
$117,160
-
Tgal
$23,800
-
gal
$2,170
-
lb
$765
TOTAL IMPLEMENTED $49,011 $4,655 $12,440
383,939
kWh
$32,016
-
kW-mo/yr
$460
-
MMBtu
$1,160
-
Tgal
- $2,170
-
lb
$765
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Personnel Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs