ITAC Assessment: AM0305
ITAC logo
ITAC Assessment: AM0305
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Storage tanks, pressure vessels, plate fabrication, painting
NAICS
n/a
SIC 3443: Fabricated Plate Work (Boiler Shops)
Sales Range $5
M
to 10
M
# of Employees 75
Plant Area 78,000
ft2
Annual Production 4,000,000
lb
Production Hrs. Annual 4,384
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $86,929 1,803,341
kWh
Electricity Demand $13,153 4,363
kW-mo/yr
Electricity Fees $483 -
Natural Gas $7,618 1,474
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $115,306 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $13,606

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
01 2.5194: Redesign process $101,500 $110,000 - - - $45,000 - $56,500
02 2.3212: Optimize plant power factor $9,350 $9,045 - $9,350
-
kW-mo/yr
- - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $2,030 $500 $2,030
88,218
kWh
- - - - -
04 3.7312: Implement a regular maintenance program to reduce emissions from leaky valves and pipe fittings $570 $20 - - $570
-
MMBtu
- - -
05 2.8121: Apply for tax-free status for energy purchases $558 - - - - - $558 -
06 2.6212: Turn off equipment during breaks, reduce operating time $395 - $395
17,292
kWh
- - - - -
07 2.7134: Use photocell controls $300 $15 $100
4,396
kWh
$200
-
kW-mo/yr
- - - -
08 4.821: Pay bills on time to avoid late fees $253 - - - - - $253 -
09 2.7142: Utilize higher efficiency lamps and/or ballasts $200 $95 $40
1,758
kWh
$160
-
kW-mo/yr
- - - -
10 2.4133: Use most efficient type of electric motors $150 $304 $12
586
kWh
$138
-
kW-mo/yr
- - - -
TOTAL RECOMMENDED $115,306 $119,979 $2,577
112,250
kWh
$9,848
-
kW-mo/yr
$570
-
MMBtu
$45,000 $811 $56,500
TOTAL IMPLEMENTED $13,606 $9,884 $2,537
110,492
kWh
$9,688
-
kW-mo/yr
$570
-
MMBtu
- $811 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs