Assessment Year | 1997 |
---|---|
Principal Product | Steel fabrication, structural steel baseplates for gas turbi |
NAICS |
n/a
|
SIC | 3441: Fabricated Structural Metal |
Sales Range | $10 M to 50M |
# of Employees | 265 |
Plant Area |
172,200
ft2
|
Annual Production | 7,204
pieces
|
Production Hrs. Annual | 3,298
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $258,792 | 4,229,191 |
kWh
|
$0.061 |
Electricity Demand | $60,713 | 20,430 |
kW-mo/yr
|
$2.97 |
Electricity Fees | $2,423 | - |
|
- |
Natural Gas | $4,358 | 950 |
MMBtu
|
$4.59 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $136,350 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $88,290 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.8114: Change rate schedules or other changes in utility service | $64,000 | - | - | - | $64,000 | - | - | - | |
02 | 3.8142: Distill contaminated solvents for reuse | $40,000 | $24,270 | - | - | - |
$40,000
-
gal
|
- | - | |
03 | 2.3212: Optimize plant power factor | $21,900 | $22,340 | - |
$21,900
-
kW-mo/yr
|
- | - | - | - | |
04 | 3.7198: Reduce / eliminate use of disposable product | $4,960 | $110 | - | - | - | - |
$4,960
-
lb
|
- | |
05 | 2.3512: De-energize excess transformer capacity | $2,070 | $300 |
$1,800
35,756
kWh
|
$270
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,880 | $300 |
$1,880
38,101
kWh
|
- | - | - | - | - | |
07 | 4.423: Move product using mechanical means | $770 | $1,460 | - | - | - | - | - | $770 | |
08 | 2.8123: Pay utility bills on time | $510 | - | - | - | $510 | - | - | - | |
09 | 2.6212: Turn off equipment during breaks, reduce operating time | $260 | - |
$260
5,275
kWh
|
- | - | - | - | - | |
TOTAL RECOMMENDED | $136,350 | $48,780 |
$3,940
79,132
kWh
|
$22,170
-
kW-mo/yr
|
$64,510 |
$40,000
-
gal
|
$4,960
-
lb
|
$770 | ||
TOTAL IMPLEMENTED | $88,290 | $22,640 |
$1,880
38,101
kWh
|
$21,900
-
kW-mo/yr
|
$64,510 | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs