Assessment Year | 1997 |
---|---|
Principal Product | Lithographic printing |
NAICS |
n/a
|
SIC | 2752: Commercial Printing, Lithographic |
Sales Range | $10 M to 50M |
# of Employees | 194 |
Plant Area |
77,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 6,096
hrs
|
Location (State) | Texas |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $113,408 | 2,056,565 |
kWh
|
$0.055 |
Electricity Demand | $18,708 | 6,360 |
kW-mo/yr
|
$2.94 |
Electricity Fees | $230 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $21,890 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $480 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7221: Lower temperature during the winter season and vice-versa | $4,800 | $3,900 |
$4,800
149,472
kWh
|
- | - | - | - | |
02 | 3.5316: Contract a wood pallet recycling company | $4,570 | - | - | - | - | - | $4,570 | |
03 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $4,320 | $1,090 | - | - |
$4,320
-
lb
|
- | - | |
04 | 2.3212: Optimize plant power factor | $2,730 | $7,020 |
$2,730
74,443
kWh
|
- | - | - | - | |
05 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $1,770 | $8,000 | - | - |
$1,770
-
lb
|
- | - | |
06 | 3.4111: Use closed cycle process to minimize waste water production | $1,720 | $75 | - |
$1,720
-
Tgal
|
- | - | - | |
07 | 2.8114: Change rate schedules or other changes in utility service | $1,500 | - | - | - | - | $1,500 | - | |
08 | 3.7198: Reduce / eliminate use of disposable product | $480 | $110 | - | - |
$480
-
lb
|
- | - | |
TOTAL RECOMMENDED | $21,890 | $20,195 |
$7,530
223,915
kWh
|
$1,720
-
Tgal
|
$6,570
-
lb
|
$1,500 | $4,570 | ||
TOTAL IMPLEMENTED | $480 | $110 | - | - |
$480
-
lb
|
- | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs