ITAC Assessment: AM0290
ITAC logo
ITAC Assessment: AM0290
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Barges, repaired & built
NAICS
n/a
SIC 3731: Ship Building and Repairing
Sales Range $10
M
to 50
M
# of Employees 260
Plant Area
n/a
Annual Production 1,750
pieces
Production Hrs. Annual 8,760
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $267,948 7,868,699
kWh
Electricity Demand $107,635 17,316
kW-mo/yr
Electricity Fees $27,541 -
Natural Gas $161,402 46,342
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,750 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $16,000

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2136: Install / repair insulation on steam lines $4,660 $920 - - $4,660
-
MMBtu
02 2.1233: Analyze flue gas for proper air/fuel ratio $3,310 $500 - - $3,310
-
MMBtu
03 2.3134: Shift from daytime to nighttime operation $3,100 - - $3,100
-
kW-mo/yr
-
04 2.4314: Use synthetic lubricant $2,130 - $1,120
50,996
kWh
$1,010
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,500 $300 - - $1,500
-
MMBtu
06 2.7124: Make a practice of turning off lights when not needed $1,300 $150 $440
19,930
kWh
$860
-
kW-mo/yr
-
07 2.6212: Turn off equipment during breaks, reduce operating time $750 - $750
34,291
kWh
- -
TOTAL RECOMMENDED $16,750 $1,870 $2,310
105,217
kWh
$4,970
-
kW-mo/yr
$9,470
-
MMBtu
TOTAL IMPLEMENTED $16,000 $1,870 $1,560
70,926
kWh
$4,970
-
kW-mo/yr
$9,470
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs