ITAC Assessment: AM0824
ITAC logo
ITAC Assessment: AM0824
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Automotive and industrial electronic controllers
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3672: Printed Circuit Boards
Sales Range greater than $500
M
# of Employees 1,600
Plant Area 343,000
ft2
Annual Production 17,800,000
pieces
Production Hrs. Annual 8,544
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,882,262 34,262,400
kWh
Electricity Demand $378,693 53,643
kW-mo/yr
Electricity Fees $66,761 -
Natural Gas $8,676 980
MMBtu
TOTAL YEARLY COSTS $2,336,392
RECOMMENDED SAVINGS* $4,760 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $3,360

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $2,660 $4,400 $2,500
45,500
kWh
$160
-
kW-mo/yr
02 2.4239: Eliminate or reduce compressed air usage $1,400 $1,855 $1,400
25,900
kWh
-
03 2.7135: Install occupancy sensors $700 $360 $700
12,500
kWh
-
TOTAL RECOMMENDED $4,760 $6,615 $4,600
83,900
kWh
$160
-
kW-mo/yr
TOTAL IMPLEMENTED $3,360 $4,760 $3,200
58,000
kWh
$160
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs