| Assessment Year | 1997 |
|---|---|
| Principal Product | Diesel engine fuel injection components, diesel engine parts |
| NAICS |
n/a
|
| SIC | 3519: Internal Combustion Engines, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 65 |
| Plant Area |
234,000
ft2
|
| Annual Production | 5,212
pieces
|
| Production Hrs. Annual | 2,394
hrs
|
| Location (State) | Texas |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $77,041 | 1,898,300 |
kWh
|
$0.041 |
| Electricity Demand | $50,386 | 7,835 |
kW-mo/yr
|
$6.43 |
| Electricity Fees | $6,006 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $27,870 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $27,870 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $21,800 | $5,500 | - | - | - | - | - |
$21,800
-
lb
|
|
| 02 | 2.3512: De-energize excess transformer capacity | $1,830 | $1,050 |
$1,590
36,928
kWh
|
$240
-
kW-mo/yr
|
- | - | - | - | |
| 03 | 2.7124: Make a practice of turning off lights when not needed | $1,330 | - |
$1,330
30,774
kWh
|
- | - | - | - | - | |
| 04 | 3.6124: Burn waste oil for heat | $820 | - | - | - | - | - |
$820
-
gal
|
- | |
| 05 | 3.4154: Eliminate leaks in water lines and valves | $650 | $50 | - | - | - |
$650
-
Tgal
|
- | - | |
| 06 | 2.8123: Pay utility bills on time | $600 | - | - | - | $600 | - | - | - | |
| 07 | 2.7124: Make a practice of turning off lights when not needed | $440 | - |
$440
10,258
kWh
|
- | - | - | - | - | |
| 08 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $230 | $100 |
$230
5,275
kWh
|
- | - | - | - | - | |
| 09 | 3.5311: Recover and reuse waste material | $170 | - | - | - | - | - |
$170
-
gal
|
- | |
| TOTAL RECOMMENDED | $27,870 | $6,700 |
$3,590
83,235
kWh
|
$240
-
kW-mo/yr
|
$600 |
$650
-
Tgal
|
$990
-
gal
|
$21,800
-
lb
|
||
| TOTAL IMPLEMENTED | $27,870 | $6,700 |
$3,590
83,235
kWh
|
$240
-
kW-mo/yr
|
$600 |
$650
-
Tgal
|
$990
-
gal
|
$21,800
-
lb
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs