ITAC Assessment: AM0288
ITAC logo
ITAC Assessment: AM0288
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1997
Principal Product Molded rubber products
NAICS
n/a
SIC 3069: Fabricated Rubber Products, Not Elsewhere Classified
Sales Range $1
M
to 5
M
# of Employees 38
Plant Area 26,000
ft2
Annual Production 600,000
pieces
Production Hrs. Annual 5,952
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $69,464 1,474,209
kWh
Electricity Demand $18,903 3,941
kW-mo/yr
Natural Gas $20,253 5,200
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $12,587 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,007

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.3134: Shift from daytime to nighttime operation $2,220 - $(-1,510.0)
(-32,825)
kWh
$5,600
-
kW-mo/yr
- - $(-1,870.0) -
02 2.2414: Use waste heat from hot flue gases to preheat $4,380 $10,440 - - $4,380
-
MMBtu
- - -
03 2.2135: Repair and eliminate steam leaks $1,580 $430 - - $1,580
-
MMBtu
- - -
04 2.7145: Install skylights $900 $2,700 $900
19,637
kWh
- - - - -
05 2.2136: Install / repair insulation on steam lines $1,200 $150 - - $1,200
-
MMBtu
- - -
06 2.8121: Apply for tax-free status for energy purchases $1,197 $800 - - - - - $1,197
07 2.1233: Analyze flue gas for proper air/fuel ratio $430 $420 - - $430
-
MMBtu
- - -
08 2.7124: Make a practice of turning off lights when not needed $380 - $260
5,569
kWh
$120
-
kW-mo/yr
- - - -
09 3.5315: Lease / purchase baler; sell cardboard to recycler $300 - - - - $300
-
lb
- -
TOTAL RECOMMENDED $12,587 $14,940 $(-350.0)
(-7,619)
kWh
$5,720
-
kW-mo/yr
$7,590
-
MMBtu
$300
-
lb
$(-1,870.0) $1,197
TOTAL IMPLEMENTED $7,007 $1,800 $(-1,250.0)
(-27,256)
kWh
$5,720
-
kW-mo/yr
$3,210
-
MMBtu
- $(-1,870.0) $1,197
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs